Clyde Pumps

Clyde Pumps



Client: Clyde Union Limited

Location: Newlands Road, Glasgow

Completed: September 2010

Project Type

  • Gas network adoption
  • New gas mains
  • Gas connection
  • Commercial gas meter installation
  • Outlet pipework

The Project

Clyde Union Limited required Fulcrum to provide a strategy to install a new gas supply, gas meter and outlet pipework to their site in Glasgow.

About The Site

Clyde Pumps' largest manufacturing facility is located in Glasgow, Scotland. It has been the city's largest employer since 1871.

Our Approach

Clyde Pumps Ltd produce high value equipment that is shipped around the globe so it was essential that our planned works did not interfere with production.  Key to success therefore were the pre-construction meetings that defined milestone targets for the works around their ongoing site production.

Communication with Glasgow City Council Roads Authority was also key as the majority of the pipe route was on an arterial route leading into the city centre.  

We delivered the work with no interference to the customer's production and with minimal impact to the residents and commercial premises close by. Fulcrum received praise from the customer and local community on completion for the speed of the works and the care taken by our engineers to minimise disruption.

The Technical Part

Fulcrum installed and adopted over 500 metres of medium pressure gas mains and gas service pipework, a medium pressure kiosk and governor meter module.  There were several significant engineering challenges including road closures, long term traffic management and obtaining Network Rail clearance for working directly underneath their rail line and bridge work.

Additionally we installed 5 metres of outlet pipework from the kiosk up to the building.

A Dedicated Delivery

Field Operations Manager, Steven McGill:

"The customer required elevated pressures to operate his pressure testing burners which were required to expand their on-site capabilities. Several utility companies had already designed and quoted a supply from the existing low pressure SGN main at the site, but these designs would have required the customer to install and maintain boosters and compressors.

Instead, I proposed installing a new medium pressure main and service to remove the need for the undesired boosters and compressors.

Although the initial one off infrastructure investment was higher, the ongoing equipment costs were permanently removed. This suited the customer requirements and Fulcrum was commissioned to complete the works."

What Our Customers Say

"When Clyde Union Pumps decided to install new gas fired steam generators for testing our range of TWL pumps, we had to look for a solution that was a bit "out of the box" for the gas supply due to the pressure and volume required to fire the generators. Fulcrum provided a solution that was both technically ideal and cost effective. They also project managed a successful installation of the gas pipeline and the metering housing that finished ahead of schedule. Not only were we delighted to have an early completion but our neighbours were also delighted not only with the minimum amount of disruption but the workmanship of the finished roadway after the pipeline was installed. This installation is an important asset for the company going forward and working with a company as professional as Fulcrum was essential to the successful and speedy conclusion of the project."

William RC Hay

Engineering and Compliance Manager

CLYDEUNION Pumps