Client: Forth Electrical Services (FES) Ltd

Location: Castle Hill, Edinburgh

Completed: April 2010

Project Type

  • Alteration to the position of the existing gas supply
  • Gas meter relocation
  • Gas network adoption

The Project

Fulcrum worked in collaboration with our customer Forth Electrical Services Ltd, Edinburgh Military Tattoo and Historic Scotland to establish the best solution for this highly prestigious building.

Reflecting our vast experience, we were selected to remove the existing gas service and design and install a gas infrastructure capable of supplying the ongoing requirements of the castle.

About The Site

Still in use today, Edinburgh Castle dominates the city skyline from its position on top of the volcanic castle rock.

Our Approach

Working closely with our customer, Forth Electrical Services Ltd, we provided a complete end-to-end service that fully considered the on site implications of the project for this historic building.

There were a variety of complexities and challenges including working with archaeologists who were investigating the discovery of previously unknown walls and ancient artefacts below the surface.

Despite this we ensured that the works were successfully completed to the customer's requirements and within the planned timescales.

The Technical Part

Fulcrum disconnected the existing ductile iron gas service and relayed the supply with over 120 metres of new gas mains and service pipe to the proposed new meter position in a kiosk at the entrance to the tunnel.

The design of this gas network was prepared by Fulcrum and adopted by Fulcrum Pipelines Limited.

A Dedicated Delivery

Design Engineer Andrew Collin:

"There were many challenges from a design perspective on this project. Not least agreeing a route with all parties that fully met the customer's requirements and ensured safety whilst minimising any impact to the historic site.

Many design options were proposed and evaluated before our final design solution was agreed. This involved on site meetings with representatives from all parties.

To deliver this successfully, we drew on our technical knowledge and experience of current regulations such as IGE/TD/3 for mains laying and IGE/TD/4 for service laying to ensure design and engineering compliance. We also considered the aesthetics of this historic building by ensuring visible pipe work was kept to a minimum."

What Our Customers Say

"Fulcrum staff are commended for their excellent high level of service provision from design to the commissioning of the gas infrastructure. Their commitment, professionalism, including the high level ofongoing customer support, provided during the project facilitated and played an integral part in assisting FES Ltd in the successful completion and timely handover for all of the projects infrastructure services."

Charles Easton

Division Director (High Voltage and Utilities Division)

FES Ltd