Heron Tower

Heron Tower



Client: Skanska

Location: 110 Bishopsgate, London

Completed: November 2010

Project Type

  • New gas connection

The Project

Working with Skanska, Fulcrum delivered a new gas supply to a prestigious building in the center of London, Heron Tower.

About The Site

Heron Tower, also referred to as 110 Bishopsgate, is a skyscraper constructed by Heron International in the City of London. Now completed it is the tallest building in London at 230m (755ft).

Our Approach

We worked in partnership with Skanska, the network National Grid Gas Plc and Transport for London, as the gas service was installed in one of the busiest areas of central London.

During the design, planning and construction, we maintained communication with Skanska to ensure their requirements were fully met and with Transport for London to minimise disruption to this busy area during the installation.

The Technical Part

Skanska required a new gas connection to offices and the restaurant Sky Bar situated on the 40th floor. To obtain the correct operating pressure we incorporated the use of boosters and compressors.

The service had to be designed to address engineering difficulties surrounding the building's construction. For example, the retaining walls at basement level were constructed in a manner that meant that the gas service had to be reduced in size to pass through pre-cast openings.

A Dedicated Delivery

Design Manager Steve Naylor:

"As the primary gas meter was to be located within the building at basement level, we had to look at ways of elevating the pressure for the equipment on the 40th floor.

Using experience obtained on previous projects of this nature I proposed the use of boosters to the client. Using boosters, it would elevate the meter pressure and we could design the system to make allowances for the pressure drop over the 40 floors.

Reflecting the way boosters operate and how they can affect the systems they are connected to, I submitted two designs to the operating gas network, one for normal conditions and one for boosted conditions.  Both designs were analysed to determine the rate at which the pressure would increase without affecting the existing network, before approval was given for the boosted option."

What Our Customers Say

"Correspondence with the design office was exceptional. We were kept fully informed of the current progress with the design and delivery of requirements. Liaison with the site agent was good, and initial site discussions on dates and install were progressive."

Kevin Walling

Senior Project Engineer (Mechanical)

Skanska

Gas Connections      Gas Disconnections       Metering       Outlet Pipework       Multi-Utility