Fulham Palace & Bishops Park

Fulham Palace & Bishops Park



Client: VINCI Construction UK

Location: Bishops Avenue, London

Completed: April 2011

Project Type

  • Gas disconnections
  • New gas connections

The Project

Fulcrum was awarded the gas infrastructure works as part ofthe regeneration project at Fulham Palace and the surrounding Bishops Park.

About The Site

Fulham Palace has been hailed as one of the most important buildings in London. The estate was owned by the Bishops of London for over 1300 years. Vacated in 1975,the Palace is now managed jointly by Hammersmith and Fulham Council and the Fulham Palace Trust.

Our Approach

We worked closely with our customer VINCI Construction UKduring the week long works to ensure we delivered to their preferred timescales at each stage of this prestigious project.

The Technical Part

Fulcrum were required to complete gas disconnections to the four existing services supplying gas to Fulham Palace and the surrounding Bishops Park while the regeneration works were carried out. 

Fulcrum then installed approximately 83m of 63mm gas mains and over 65m of 32mm gas service pipe to supply the newly regenerated Club House, Ground Stable block, café, Palace adventure playground, Old Rainbow Play Hut and Gothic Lodge.

A Dedicated Delivery

Field Operations Manager Gary Priestnall:

"Although this wasn't a technically difficult job, the developer was carrying out all the excavations on site which required a large amount of co-ordination.

I met with VINCI Construction UK to walk the site prior to the project commencing. It was agreed that the works would be completed during a five day period, in a specified order that met with the archaeological conditions. All excavations were carried out under the eye of an archaeological surveyor who was on site throughout to sample the ground for items of interest.

The project was completed as agreed, apart from Gothic Lodge which was delayed when the archaeological surveyor stopped works when items of interest were discovered. We returned to site the following week to complete the project once the surveyor had given the site clearance to continue excavations."

What Our Customers Say

"We would like to thank Gary and his team for their efforts in being a part of this successful project. This project was particularly sensitive due the archaeological discoveries.  Gary's teamwere sensitive and supportive of our Clients interest and requirements."

Matt Stevenson

Project Manager

VINCI Construction UK

Gas Connections      Gas Disconnections       Metering       Outlet Pipework       Multi-Utility