Moon Crescent Development

Moon Crescent Development



Client: CKC D&B Ltd

Location: Brookhill Leys, Nottingham

Completed:May 2011

Project Type

  • Multi-Utility connections (gas connections, electricity connections and water connections)
  • Domestic gas meter installations
  • Domestic water meter installations
  • Streetlighting
  • Gas network adoption

The Project

Fulcrum was approached by CKC D&B Ltd to provide a multi-utility connection package to a domestic development named 'Moon Crescent' located in Nottingham.

About The Site

The £5m development was funded by the Homes and Communities Agency and Nottingham Community Housing Association. This development which created  40 new homes, was on the old Moon and Stars pub site and the reason for adopting the name 'Moon Crescent'.

Our Approach

Over a five month period Fulcrum supported CKC D&B Ltd's build programme working closely, to ensure we completed the delivery of works within the desired timeframe.

The Technical Part

The customer required Fulcrum to install over 220 metres of gas, water and electricity mains which had 40 individual domestic services branching off the mains to supply the 40 new properties. 

In addition, Fulcrum designed and coordinated a sub-station installation by the Network, installed 6 street lights and fitted the new gas and water meters.

The gas network was also adopted by Fulcrum Pipelines Limited.

A Dedicated Delivery

Multi-Utility Project Delivery Manager Dean Pattison:

"We worked very closely with CKC D&B Ltd throughout the project so that we had clear visibility of the build programme and expectations.

As a Housing Association funded project, the target completion dates were very specific and required Fulcrum to construct all three utilities in a time efficient and coordinated manner.  A number of obstacles were identified throughout the build requiring Fulcrum to adopt a proactive approach and provide ongoing solutions to the client."

What Our Customers Say

"Taking the plunge with multi-utility felt like a step into unchartered territory for CKC but Fulcrum managed our fears and delivered our scheme at Eastwood with, dare I say, surprising ease! Many contractors and developers will have experienced the minefield of statutory services and will have witnessed their staff's desperation at the timelost chasing what can seem an unending circle of dead ends, misinformation and ridiculous lead times. This constant frustration led CKC to the decision to let Fulcrum manage all of the services on our behalf and I can honestly say that the end result was very pleasing indeed.

Our scheme was delivered with punctual information updates which were not only accurate but enabled improved site programming. Services were installed in multi use trenches thus negating the need to interrupt site activities as would have been the case with individual providers and hence our overall programme was maintained. Fulcrum's Multi-Utility team have a wealth of knowledge just waiting to be utilised and it is this insight which gives them the ability to stay ahead of the market and actually deliver what they say they will and when."

Peter Holden

Construction Director

CKC D&B Ltd